Mid November 2004
Great progress is being made on the Windmill site and the project
is on target for completion date of 17 th December.
The 3 foundations for the windmills were dug out last week and this
weekend saw tonnes of concrete being mixed and poured into the foundations.
The
foundations rings, to which the windmills will be secured, were
placed in the foundations and concreted in place. Delivery of the
turbine parts starts Friday 19 th ….

Next pictures of the actual turbines going up ...
|